For Solariz Egypt, ADVEC delivered the full electrical compliance package for the 1 MWp metering PV system at Coca-Cola’s Qalyuib facility. The team completed its technical scope in 2023, preparing a grid code compliance study customized for the factory’s operational setup and metering configuration.
The project reached full completion after ADVEC finalized the grid impact analysis and recommendations, marking it as an accomplished milestone for industrial solar integration. Engineers conducted a detailed grid impact study, evaluating short-circuit levels, load flow, reactive power capability, power quality, and transient performance, ensuring stable solar generation and compliance with Egyptian grid regulations.